The U.S. Supreme Court declined a request from Massachusetts residents to review a lower court’s rejection of their challenge to federal approval of offshore wind turbines that generate electricity.
The residents argued that a wind farm in the Cape Cod community was placing an endangered species of whale, the North Atlantic right whale, at risk and that federal agencies failed to follow the law when assessing the environmental impact of the project. They also said the turbines were damaging the local environment.
The Bureau of Ocean Energy Management (BOEM) is an agency inside the U.S. Department of the Interior.
The federal government approved locating the country’s first utility-scale offshore wind turbine project, known as Vineyard Wind 1, 15 miles off the coast of Nantucket. The project is owned by Avangrid and Copenhagen Infrastructure Partners, which do business through Vineyard Wind LLC, which in turn is building Vineyard Wind 1, according to the petition.
The project is promoted as the first of the government’s “coordinated steps” to build about 30 wind turbine projects “along the Atlantic seaboard that, when built out, will have thousands of turbines covering millions of acres of federal submerged lands.”
Vineyard Wind LLC has built or is in the process of building 47 of the total of 62 approved fixed-bottom wind turbines. Each turbine rises 853 feet above the water and is almost triple the size of the Statue of Liberty.
The petition states that the 47 turbines are already harming the environment. For example, in July 2024 a large piece of a 350-foot blade broke off from one of the turbines and fiberglass shards from the blade littered Nantucket’s beaches. Also, the turbines may threaten the endangered North American right whale, only 388 of which still exist, by interfering with their habitat and migratory routes, according to the petition.
Moreover, even though federal law requires the government to examine the “best information available” regarding the impact that a project may have on an endangered or threatened species and their habitats, the BOEM and National Marine Fisheries Service (NMFS) failed to consider the “cumulative impacts of other planned projects when they authorized and issued permits to construct the Vineyard Wind 1 Project,” according to the petition.
The residents say the agencies that leased the water area to wind energy companies left relevant data out of their assessment so they could facilitate offshore wind energy development.
And, contrary to the residents’ argument, the decision of the First Circuit does not conflict with existing decisions of the Ninth Circuit and District of Columbia Circuit, the brief stated.
The U.S. Department of Justice, which represents BOEM, declined to weigh in on the new ruling.
“We don’t have a comment,” Matthew Nies, a public affairs specialist at the department, told The Epoch Times on Jan. 16.
The Epoch Times reached out to the residents’ attorney, Nancie Marzulla of Marzulla Law in Washington, but no reply was received by publication time.